Tapestry says HyperQ screened PJM's Cycle 1 site-control documents in under a day

Tapestry says its AI tool checked the land-rights papers of 811 PJM applications, about 220 GW, in under 24 hours, against two months by hand.

Tapestry, the grid software company that began at Alphabet's X, said on 10 November 2026 that its HyperQ AI tool has finished screening the site-control documents of all 811 generation applications in Cycle 1 of PJM Interconnection's reformed interconnection process, about 220 GW of proposed capacity.

Site control is proof that a developer is legally entitled to build on a particular plot. Under PJM's new first-ready, first-served rules, a project must show it is viable before it is studied, with up-front financial commitments and site control among the tests, PJM says. The Cycle 1 application window closed on 27 April.

Tapestry says HyperQ ran alongside a manual review of the same 811 applications and produced a readiness report for each, with page-level citations, at a median of 6 minutes 15 seconds per application. It compares under 24 hours with about two months for the same intake and first review done by hand, a 60-fold speed-up. The point of the comparison, Tapestry says, is that this paperwork step can stop being a bottleneck: applications without land rights are caught before engineering studies begin, and PJM's reviewers spend less time hunting through documents. PJM, in a statement Tapestry quotes, said the early results look promising as a basis for the speed it needs to meet its goal of a 12-month interconnection timeline, with its own experts kept fully in control.

Tapestry says HyperQ grouped 4,581 documents into 2,328 agreement bundles and checked each against four site-control tests in PJM's tariff, covering contract term, chain of title, exclusive use and minimum acreage: 9,312 assessments in all. PJM's experts make every final compliance decision, and about 202 GW moved on to Phase 1 of the studies, Tapestry says. Its figures cover only the site-control stage, not engineering studies or final approval times.

PJM said on 3 August that 715 projects totalling more than 200 GW had qualified for study in a cycle designed to take one to two years, and that it would assess the tool's effect across Cycle 1. Tapestry says it next plans to apply HyperQ to single-line diagrams and other engineering files, and to let developers check their applications before they submit them.