Grid connection rules for data centres
Grid operators and regulators are setting new terms for connecting data centres and other large electricity users. This tracker lists each decision, proposal and outlook we have checked at its source, newest first, with a link to the original document.
Updated 19 Nov 2026
- 19entries in 16 jurisdictions
- 8rules decided or in force
- 9proposals awaiting a decision
- 2demand outlooks
New rules and proposals by month
What the rules ask of large users
Size at which the rules apply
- 10 MWIESO (Ontario)
- 40 MWOfgem (Great Britain)
- 50 MWNCUC and Duke Energy (North Carolina), PJM, CAISO (California), NYISO (New York), ISO New England
- 75 MWPUCT (Texas), ERCOT (Texas)
All entries
- North Carolina, USAFinal
North Carolina Utilities Commission (NCUC); Duke Energy
North Carolina's utilities commission approved a rate schedule of its own for Duke Energy data-centre customers above 50 MW, adding upfront payments for dedicated facilities, financial terms tied to transmission upgrades and security against stranded generation costs.
- Upfront payment or security
Source: North Carolina regulators approve more cost-effective path to strengthen reliability and power the state’s future · Our article · First listed 18 Nov 2026
- PJM region, USAProposal
PJM Interconnection
PJM asked FERC to require data centres and other computing loads of 50 MW or more to stay connected through voltage and frequency disturbances from 16 Jan 2027, after data centres drawing nearly 3.9 GW switched to on-site generators during a grid disturbance on 22 July.
- Grid-support duties such as ride-through
Source: PJM Proposes New Rules to Protect Grid Reliability as Data Center Demand Grows · Our article · First listed 18 Nov 2026
- PJM region, USAProposal
PJM Interconnection
PJM filed a plan with FERC to cut projected study time for new generation and big users such as data centres to one year from two, moving stricter readiness and financial requirements earlier and adding new kinds of transmission service for big users that run their own generation or can reduce demand.
- Proof of project readiness
- Upfront payment or security
- Flexible connection that can be curtailed
- Own or on-site generation
Source: PJM Plan Would Cut Interconnection Process Time in Half · Our article · First listed 18 Nov 2026
- California, USAProposal
California ISO (CAISO)
CAISO asked FERC, under docket ER27-532, to treat any site whose peak reaches 50 MW or more as a large load, letting such sites connect on curtailable interim service before their network upgrades are built, alongside ride-through, deposit and readiness rules.
- Flexible connection that can be curtailed
- Grid-support duties such as ride-through
- Proof of project readiness
- Upfront payment or security
Source: Nov 16, 2026 Tariff amendment - large loads (ER27-532) · Our article · First listed 18 Nov 2026
- New York, USAProposal
New York Independent System Operator (NYISO)
NYISO filed large-load rules with FERC (docket ER27-517). Under the plan it presented to members in October, a new load of 50 MW or more that strains supply gets firm service only if it pairs with new resources, and otherwise takes service that is cut back when the local price passes $200 per MWh.
- Flexible connection that can be curtailed
- Own or on-site generation
Source: Federal Register: FERC combined notice of filings (19 Nov 2026) · Our article · First listed 19 Nov 2026
- New England, USAProposal
ISO New England
ISO New England filed rules with FERC (docket ER27-484) under which loads of 50 MW or more connected above 60 kV either supply matching new capacity to get firm service or take non-firm service that must cut back when local prices reach $250/MWh, with comments due 4 Dec 2026.
- Flexible connection that can be curtailed
- Own or on-site generation
- Upfront payment or security
- Grid-support duties such as ride-through
Source: ISO-NE files proposal with FERC to address ‘large loads’ · Our article · First listed 18 Nov 2026
- Ontario, CanadaProposal
Independent Electricity System Operator (IESO)
The IESO issued for stakeholder review a draft Market Rule amendment setting ride-through, ramp-rate and other technical requirements for computing facilities over 10 MW, to be presented at a webinar on 19 Nov 2026.
- Grid-support duties such as ride-through
Source: Technical Requirements for Large Computational Loads Connecting to the Ontario Power System · First listed 18 Nov 2026
- NorwayIn force
Statnett
Statnett stopped reserving more grid capacity for data centres and paused new applications for approval of their facility functions, expecting to lift the pause by 1 Aug 2027 at the latest, while existing connections are unaffected.
- Queue pause or waiting list
Source: Midlertidige tiltak for fortsatt forsvarlig systemdrift · Our article · First listed 18 Nov 2026
- Québec, CanadaPlan or outlook
Hydro-Québec
Hydro-Québec's 2027–2041 supply plan forecasts that data centres in Québec will need 1,977 MW at the winter peak in 2040–41, up from 353 MW in 2025–26.
Source: Plan d’approvisionnement 2027-2041 en réseau intégré (R-4359-2026, HQD-2, Document 1) · Our article · First listed 18 Nov 2026
- DenmarkIn force
Energinet
Energinet said it would answer connection applicants in November under four priority categories set by new Danish law, after pausing new large connections in March, and warned that full grid access looked hard for the lowest categories, which cover storage and other large consumers, so it is developing flexible or limited-access connections to fit in more batteries and data centres.
- Queue pause or waiting list
- Flexible connection that can be curtailed
Source: Energinet gør klar til prioriteret kapacitetstildeling og tager nye virkemidler i brug · First listed 18 Nov 2026
- SpainPlan or outlook
Red Eléctrica
Red Eléctrica published a map of demand access to Spain's transmission grid showing that data centres hold 6,329 MW of granted access, 34.2% of the total, none of it yet in service.
Source: Red Eléctrica publishes the demand access capacity map by consumption type · First listed 18 Nov 2026
- Texas, USAFinal
Public Utility Commission of Texas (PUCT)
The PUCT adopted a rule, 16 TAC §25.194, requiring large loads of 75 MW or more to sign an interim agreement, make disclosures and post $50,000 per MW in security before ERCOT studies them, then sign a standard interconnection agreement and pay contributions towards direct connection costs.
- Upfront payment or security
- Proof of project readiness
Source: Project No. 58481, Rulemaking to Implement Large Load Interconnection Standards under PURA §37.0561: Order Adopting New 16 TAC §25.194 · First listed 18 Nov 2026
- Texas, USAIn force
ERCOT
ERCOT told its board that, following the Texas governor's 3 Aug 2026 directive, it has paused approvals to energise new data centres and crypto-mining sites of 75 MW or more until an eligibility audit and a community-impact review are complete, with both reports due to the PUCT by 10 Dec 2026.
- Queue pause or waiting list
- Proof of project readiness
Source: Item 14: Batch Zero Update (ERCOT Board of Directors Meeting, September 14-15, 2026) · First listed 18 Nov 2026
- MISO region, USAProposal
Midcontinent Independent System Operator (MISO)
MISO reported that it asked FERC on 28 Aug 2026 (ER26-3650) to approve grid-connection reliability rules for large loads from 4 Dec 2026, and on 18 Aug (ER26-3552) a separate agreement for zero-injection generators serving load at the same substation.
- Own or on-site generation
Source: Large Load Working Group: FERC Status Report, September 9, 2026 · First listed 18 Nov 2026
- Alberta, CanadaProposal
Alberta Electric System Operator (AESO)
The AESO said it is still finalising a 'bring your own generation' connection process for big users such as data centres, with documents and application intake expected in autumn 2026, building on Phase I, which set a 1,200 MW interim connection limit in June 2025.
- Own or on-site generation
- Proof of project readiness
Source: Phase 2A: Large Load Integration | BYOG Process · First listed 18 Nov 2026
- SpainIn force
Comisión Nacional de los Mercados y la Competencia (CNMC)
The CNMC approved flexible access permits that let new electricity consumers connect where no firm capacity is available, on condition that they cut or adapt their use at certain times, with the resolution taking effect on 1 Sep 2026.
- Flexible connection that can be curtailed
Source: La CNMC aprueba la regulación que facilitará la conexión de nuevos consumidores a la red eléctrica mediante permisos de acceso flexible · First listed 18 Nov 2026
- Great BritainProposal
Ofgem
Ofgem consulted on a returnable commitment fee of roughly £237,500–£712,500 a MW for data-centre projects above 40 MW, and on queue milestones requiring proof of a credible end user, orders placed for long-lead electrical gear, and the money and technical ability to build.
- Proof of project readiness
- Upfront payment or security
Source: Proposed data centre connection reforms · First listed 18 Nov 2026
- GermanyFinal
50Hertz, Amprion, TenneT Germany, TransnetBW
Germany's four transmission system operators announced that, from 1 Apr 2026, extra-high-voltage connection requests from storage, data centres and other large users would be judged by project maturity in fixed application cycles instead of first come, first served.
- Proof of project readiness
Source: Übertragungsnetzbetreiber führen „Reifegradverfahren“ für Netzanschlussanträge von Speichern und Großverbrauchern ein · First listed 18 Nov 2026
- IrelandFinal
Commission for Regulation of Utilities (CRU)
The CRU decided that new data centres must provide generation or storage, on site or nearby, matching their maximum import capacity, and must source at least 80% of yearly demand from additional renewable projects in Ireland.
- Own or on-site generation
Source: The CRU Publishes its Decision on New Electricity Connection Policy for Data Centres · First listed 18 Nov 2026